Fast Pace Turnkey Solution for Nordana
RayClean™ on Board the M/V Brattingsborg
DESMI Ocean Guard demonstrated great agility and pace as a loose component project with the shipowner, Nordana, evolved into a full turnkey solution delivered and commissioned in just four months - from first inspection to final commissioning.
From September 2015 to January 2016, DESMI Ocean Guard prepared and installed a RayClean™ 300 system along with a wide range of associated components under time pressure and difficult circumstances.
The turnkey solution involved a thorough ship inspection in Italy, 3D scanning in Norway, engineering, manufacturing, and installation of the tailored components, class approval, delivery and installation of loose components in China, and handover in Singapore. This project quickly evolved and when the need for flexibility emerged, DESMI Ocean Guard managed to beat the usual production time.